Pokko Hydropower Project, 124.5 MW – Indonesia

Home > Hydropower and Dams > Pokko Hydropower Project, 124.5 MW – Indonesia

Project

The proposed Project is located in the central-western part of Sulawesi Island, on the Mamasa River, approximately 22 km upstream of the existing Bakaru Hydropower Plant dam. Based on the preliminary design, the main project components include:
an RCC dam with a curved axis and a height of 126 m, extending from the dam crest elevation of +826 m to the main foundation level at +700 m; a power waterway system comprising an intake structure, a 178 m long headrace tunnel, a 184 m pressure shaft/tunnel, a surge tank, and a 2.25 km long tailrace tunnel; an underground powerhouse equipped with three turbine units with a total installed capacity of 124.5 MW, including an access tunnel and transformer cavern; a 150 kV transmission line approximately 26 km long.

Client

PT Perusahaan Listrik Negara, PERSERO.

Services

  • Stage I: Review of the Feasibility Study and scope of works for additional investigations.
  • Stage Il: Additional investigations
  • Stage III: Detailed Design
  • Stage IV: Market Analysis and Procurement Strategy
  • Management and Supervision of the following additional investigations:
  • Management and Supervision of the following additional investigations:
    • Additional geological site investigations and laboratory testing, including excavation of exploratory adits and insitu testing
    • Physical hydraulic model tests of dam and spillway
    • Topographic Survey (LiDAR) of the Project Area including reservoir area, access road, and transmission line

Status

In Progress