Installed capacity 460 MW (4×115 MW Francis turbines), underground powerhouse, power and tailrace tunnel totaling 19 km, 7.2 m diameter (excavated with TBM).
Client
Ethiopia Electric Power, EEP
Services
Review of Basic Design
Review of Detailed Design
Review of Environmental and Social Management Plan of the EPC Contractor
Construction Supervision
Contract Management
Commissioning
Assistance to Client in Bidding Evaluation and contract Negotiation