This Project is the first hydropower plant construction project in Dohuk Governorate and is located on the Greater Zab River in the Zagros Mountains, Kurdistan region. Deralok Hydropower Plant is a Run-off-River Type Hydropower Plant with a total capacity installed of 37.6 MW and the associated 132 kV Transmission Line. The project discharge is 220m³/s, two turbines of 18.8 MW each, Kaplan-type.
Financed by Japan Internationa Cooperation Agency, JICA.
Client
Regional Ministry of Electricity in Kurdistan, RMEK
Services
Review of the original Feasibility Study and Detailed Design
Tender Documents Preparation and support to the Client for the Contractor Selection
Management of the Contract on behalf of the Client including Analysis of the Contractor’s Claims and Assistance to the Client regarding Quality Cost and Time
Supervision of the Civil Works Construction and Electromechanical Equipment Erection Activities
Quality assurance
Workshops on Dam Monitoring and Dam Safety Panel Implementation