Project

General Rehabilitation of 400 MW hydropower plant (5×80 MW Francis turbines).
Financed by International Development Association, IDA with cooperation World Bank, WB.

Client

Ministry of Electricity, Kurdistan Regional Government

Services

  • Procurement
  • Rehabilitation Plan
  • Work Supervision in Dam and Plant in Controlling and System Monitoring Phase
  • Transfer of Knowledge to Client’s Staff

Status

In Operation