Gilgel Gibe I Hydropower Project, 189 MW – Ethiopia

Home > Hydropower and Dams > Gilgel Gibe I Hydropower Project, 189 MW – Ethiopia

Project

Installed capacity 189 MW (3×63 MW Francis turbines), power tunnel 9 km long, 5.5 m diameter (D&B method).

Client

Ethiopia Electric Power, EEP

Services

  • Pre-feasibility and Feasibility Study
  • Review of Basic Design
  • Review of Detailed Design
  • Review of Environmental Impact Assessment
  • Construction Supervision
  • Contract Management
  • Supervision and Assistance during Commissioning
  • Assistance to the Client in Bidding Evaluation and Contract Negotiation
  • Transfer of Knowledge to Client’s Staff

Status

In Operation