Rogun Hydropower Project, 3,780 MW – Tajikistan

Home > Hydropower and Dams > Rogun Hydropower Project, 3,780 MW – Tajikistan

Project

World’s highest rockfill dam 335 m;
Installed capacity of 3,780 MW (6×630 MW Francis turbines);
Six independent power waterways 460 to 570 m long;
Underground powerhouse 20 m long, 70 m high and 25 m wide;
Four diversion tunnels;
Total spillway capacity of 6,900 m³/s through four independent spillways.

Client

Barki Tajik (for the Phase I: Techno Economic Assessment Studies) – OJSC Rogun HPP with participation of Project Management Group for Construction of Energy Facilities under the President of the Republic of Tajikistan (for Phase II: Consultancy Services related to Employer’s Representative)

Services

  • Phase I:
    • Techno-Economic Assessment Study,
    • Preparation of Tender Documents and Assistance to Contract Signature for the Main Works;
  • Phase II:
    • Employer’s Representative during the implementation stage and the construction of the main works
  • Transfer of Knowledge to Client’s Staff.
  • Status

    Phase I Completed, Phase II in Progress